TAHAMAH CEMENT PLANT - SAUDI ARABIA


  • Capacity: 1,700,000 t/y Greenfield Plant
  • Limestone Crusher: 1,200 t/h
  • Corrective Material Crusher: 500 t/h
  • Raw Material Grinding: 400 t/h
  • Kiln Plant: 5,000 t/d
  • Cement Mills: 2 x 150 t/h
  • Captive Power Plant: (7+1) x 7 MW capacity (Diesel / HFO)
 
  • Project Implementation Monitoring Consultancy
    Approval of Design
    Pre-shipment Inspections
    Supervision of Works on Site
    Start-up and Commissioning
  • Main Contractor: Sinoma International